Chandrayaan 3 LIVE updates: Vikram Lander’s health normal, just 113 km away from Moon

Chandrayaan-3 mission detailed timeline

Chandrayaan 3 mission schedule

• July 6: ISRO announces Mission Chandrayaan-3 launch date of July 14 from Sriharikota’s second pad.

• July 7: Successful vehicle electrical tests completed.

• July 11: Comprehensive 24-hour ‘Launch Rehearsal’ simulating the entire launch process concludes.

• July 14: LVM3 M4 vehicle launches Chandrayaan-3 into designated orbit.

• July 15: First orbit-raising manoeuvre successful, reaching 41762 km x 173 km orbit.

• July 17: Second orbit-raising manoeuvre places Chandrayaan-3 at 41603 km x 226 km orbit.

• July 22: Fourth orbit-raising manoeuvre establishes spacecraft in 71351 km x 233 km orbit.

• July 25: Another successful orbit-raising manoeuvre.

• August 1: Chandrayaan-3 inserted into translunar orbit (288 km x 369328 km).

• August 5: Successful lunar orbit insertion (164 km x 18074 km).

• August 6: Lunar orbit lowered to 170 km x 4,313 km.

• August 9: ISRO carefully moves the spacecraft’s path lower in its orbit around the moon. It has achieved a lunar orbit of 174 km x 1437 km

• August 14: Chandrayaan-3 gets closer to the moon’s surface in another controlled bringing it in a orbit of 150 km x 177 km

• August 16: The Indian spacecraft performs the fifth and final Moon-bound manoeuvre positioning itself in a near circular Lunar orbit of 163*153 km.

• August 17: The landing module, comprising the Vikram lander and Pragyan rover, gets separated from its propulsion system.

• August 18: The Chandrayaan-3 will make the final orbit adjustment by reducing it to be around 100*30 km, the farthest and nearest point from the moon respectively.

• August 23: If everything goes well, planned lunar touchdown attempt at 5:47pm where the spacecraft will travel the last 30km distance.

Source link